Grizebeck has turned a corner with most of the drainage now in including steel work with mesh and bent bar in place and concrete going in.
Block work to the retainer and extension will start tomorrow and finally feel like we are getting somewhere.
(most of the work to date has been hidden, underpinning,drainage and foundation work)
Now all the infrastructure is in place we hope to progress quickly to roof level .
Mill gate is finally moving forward again with final excavations for the garage taking place in readiness for the reinforced garage retaining wall.
Again we can get the reinforced garage retaining wall in and move to the easier block wall construction.
The Coniston site has also come on well, despite the weather we are finally out of the very wet conditions and above ground floor level and going up.The floors went in very quickly with the use of the
telehandler to lift the T beams in place,it make for a speedy and sound floor construction.